Construction program

1.The working temperature is not less than 5℃.

2.Can not be in the heavy rain or temperature higher than 30℃ and the wall with direct sunlight to work.

3.Should avoid to

4.It should not have oil emulsion ash,empty drum in the wall.

5.Eject horizontal line,V Lines,draw datum line.

6.According to the technology and requiments,Making up the Bonding Mortar.Making up should be finished in a certain time.

7.We can choose Point box Method and Strip Adhibiting Method,Paste Dimensions can not be less than 40%.

8.If the size is large enough,we can use GAC Line method,clip the threaded nail on the wall.then press on the line with moratar,or use

anchor fixed.The adhering gap of special mortar should be less than 2mm between 2 lines.

9.After the line installed,it should be planished.You can use binding tape working fastening.tear it dowm after 4 hours later.

10.The helight of the line should be less than 1.5mm.Otherwise,it need to be polished.